• Kohl’s completed a new build-to-suit distribution  facility in Etna, adding 1.2 million sq. ft. of inventory to the market. They are expected to occupy in Q3.

• Hillwood finished work on a new speculative 845,000 sq. ft. warehouse in West Jefferson.

• Becknell Industrial completed a new speculative 151,000 sq.ft warehouse in the Southwest submarket.

• Xebec delivered over 530,000 sq.ft of new speculative warehouse space at Rickenbacker:

  Building 1 – 231,664 sq. ft.

  Building 2 – 136,315 sq. ft.

  Building 3 – 163,493 sq. ft.

• Xebec’s largest project under construction (1 MSF) is expected to deliver in Q3.